PROJECT A-4

In Situ Sub-Surface Soil and Groundwater Treatment
Automobile Dealership, Danvers, MA

PROBLEM:
Hydrocarbon contaminated soils and groundwater present after underground storage tank removal

A release of petroleum hydrocarbons to the environment was discovered upon the removal of four under-ground storage tanks (two gasoline and two waste oil) at a car dealership. During the removal process, total organic vapor readings exceeded 100 ppm, thus triggering the 72-hour notification requirement according to the clean-up regulations in Massachusetts. The Massachusetts DEP gave authorization to conduct an Immedi-ate Response Action (IRA) for the site. Upon removal of the tanks, visible holes were identified in all of them. Also, soil samples taken from each of the tank excavations indicated petroleum hydrocarbons in excess of reportable concentrations.

SOLUTION:
In situ application of MicroSorb® SC and MicroSorb® Biocatalyst

To determine the extent of the release, four monitoring wells were installed in and around (both upgradient and downgradient) the excavations. (Little or no contamination was found in the soils or groundwater at these locations.) Because of the number of buried utilities in the area, additional soil removal from the former tank locations was not a viable solution to the contamination problem. The in situ application of MicroSorb microbial products was determined to be the most cost effective and timely solution as a remedial IRA. An infiltration system of slotted pipe was installed at the top of the contaminated zone in both former tank excavations. At grade, a 1,000-gallon bioreactor tank was set up and supplied with 20 pounds of MicroSorb® SC (Super Concentrate), MicroSorb® Nutrients, water, and 220 gallons of MicroSorb® Biocatalyst. The bioreactor discharged to the injection piping bathing the contaminated areas with microbes, nutri-ents, and biocatalyst (source of oxygen). This liquid stream was collected downgradient at the groundwater table by means of a recovery well that would then pump the recovered (treated) groundwater back into the bioreactor tank for recirculation to the injection trenches. A second application of microbes, nutrient, and biocatalyst was applied after 30 days.

RESULTS:
After three months, non-detect levels of EPH, VPH, and targeted VOCs

After three months of operation, groundwater was sampled from the system with non-detect levels of EPH, VPH, and targeted VOCs. Confirmatory drilling indicated all groundwater samples and soil samples (except one minor EPH aliphatic soil sample violation) met risk characterization standards for closure. A Class A-2 Response Action Outcome (closure) was submitted for the site.

 

© 1996-2002 MicroSorb Environmental Products, Inc. All rights reserved.

Download the MicroSorb Brochure